Update - Boyertown Area Senior High Memorial Stadium

Boyertown Area Senior High (BASH) Memorial Stadium grandstand (home bleachers) have recently been closed due to a structural study being performed, assessing its structural integrity. The grandstand, as well as the outside six lanes of the Memorial Stadium Track – grandstand side will be unavailable until further notice as the final report is being completed.

Additional information will be shared as the district receives a full report from the engineering firm conducting the study and the Boyertown Area School District (BASD) Board of School Directors (BOSD) has had the opportunity to review and decide what the most appropriate action be in addressing the recommendations from the firm. Should you have any questions regarding Memorial Stadium use as well as the current structural study, please feel free to attend the BASD BOSD Facilities Committee meeting being held at 7:30 p.m. on Tuesday, January 30, 2018 in the Central Office Administration Building/Education Center.


Temporary arrangements are currently being made for spring and summer functions/events that have been scheduled for Memorial Stadium in the event its unavailable use extends into those time frames. Information regarding specific events will be shared once the BASD BOSD has made an informed decision relative to the engineering firm’s recommendations.


Updates from May 1, 2018 Facilities Committee Meeting

Memorial Stadium Options for Fall 2018
Memorial Stadium - Barry Isett & Associates Presentation


Updated timeline shared at the Board of School Directors Meeting on April 10, 2018

January 9, 2018
Barry Isett & Associates completed a site visit to Memorial Stadium to review the exposed probes and determine the condition of the beam and the bearing on the masonry walls

January 10, 2018
Initial Findings and Safety Memorandum provided to BASD

January 30, 2018 
Facilities Committee Meeting, Memorial Stadium Update to the Board

February 6, 2018 
Barry Isett proposal for professional engineering services received

February 20, 2018
Facilities Committee Meeting, Memorial Stadium update and review of Barry Isett proposal

February 26, 2018
Signed Contract with Barry Isett to complete structural analysis and present back to the BASD BOSD

Time line to complete analysis 6 -8 weeks

April 10, 2018 
Tom Slowik, Senior Forensic Engineer, Barry Isett to present an update on Memorial Stadium to Board.
Result of this meeting is that the projected date for full report pushed back 6-8 weeks (week of June 12)
Further testing required due to findings in the bleacher seating area

May 1, 2018 
Facilities Meeting, update from Barry Isett to be presented to committee if any new information is available

May 8, 2018
Board Meeting, update from Barry Isett if there is any new information to be shared

June 12, 2018
Projected date of completed report from Barry Isett

Projected Next Steps

Board to vote to put out RFP, then a month or so later district gets bids
Board votes to accept a bid
Ground break to begin repairs
Project complete

Barry Isett & Associates gave a presentation at the April 10, 2018 Board of Directors Meeting

Boyertown Area School District Memorial Stadium - Structural Analysis and Schematic Design of Repairs as presented at the April 10, 2018 Board of Directors Meeting.


Timeline shared at Facilities Committee Meeting on March 27, 2018

January 9, 2018
Barry Isett & Associates completed a site visit to Memorial Stadium to review the exposed probes and determine the condition of the beam and the bearing on the masonry walls

January 10, 2018
Initial Findings and Safety Memorandum provided to BASD

January 30, 2018
Facilities Committee Meeting, Memorial Stadium Update to the Board

February 6, 2018
Barry Isett proposal for professional engineering services received

February 20, 2018
Facilities Committee Meeting, Memorial Stadium update and review of Barry Isett proposal

February 26, 2018
Signed Contract with Barry Isett to complete structural analysis and present back to the BASD BOSD.  Time line to complete analysis 6 -8 weeks

April 10, 2018
Tom Slowik, Senior Forensic Engineer, Barry Isett to present an update on Memorial Stadium to Board

Week of April 23, 2018
Projected deadline for findings from Barry Isett

May 1, 2018
Facilities Meeting, projected proposal of findings from Barry Isett to be presented to committee

May 8, 2018
Board Meeting, projected date to vote on next steps with Memorial Stadium

Projected Next Steps:
1)  Board to vote to put out RFP
2)  A month or so later district gets bids
3)  Board votes to accept a bid
4)  Ground break to begin repairs
5)  Project complete